We bought some lumber today, about $440 for 30 - 2x4x10 and 6 - 2x4x16 lumber. That was probably $100-150 more than it would have been 2 years ago. But it is what it is. We used 2/3 of it to build the main living room that backs to the master bedroom closets, and the wall to its left which is the wall between the dining and laundry room. Hal wanted to get the laundry room wall up so he could finish the rough plumbing and as it is attached to the living room wall that also needed to go up first. Once he's finished the plumbing, we'll go back to installing more subflooring.

He will only be able to glue the pipes together if the temps are above 40 degree which doesn't look good tomorrow, so it's possible we'll be building the other TV room wall tomorrow. That is what the other third of the lumber we purchased is for.

But here we have the main interior wall. Hal is standing in the doorway into the master suite. 

main interior wall